Axess Group supports Altera Infrastructure in preparing FPSO Petrojarl Kong and FSO Yamoussoukro for redeployment

MOLDE, Norway, July 8, 2025 – For the past two years, Axess Group has supported Altera Infrastructure in preparing FPSO Petrojarl Kong and FSO Yamoussoukro for redeployment on Eni‘s Baleine field located offshore Côte d’Ivoire.

Multiple entities were involved in executing the following scopes: a condition assessment of the FPSO in the United Kingdom, followed by repair and life extension, baseline inspections of the FPSO and FSO in Dubai, UAE, and crane refurbishments, as well as hook-up and commissioning upon arrival in Côte d’Ivoire.

Axess Group established a company in Côte d’Ivoire in 2025, building local competence and capacity, while demonstrating its commitment to the continued development of Africa’s oil and gas industry.